Illinois  |  Construction Law

Legal Question

Asked on: 7/30/13, 2:52 pm

I'm sending a letter to a contractor demanding a mechanics lien to be released or to bring a lawsuit.

I will add the following: "Failure to respond to this notice within 30 days after receipt, as required by Section 34 of the Mechanics Lien Act, shall result in the forfeiture of the referenced lien."

Do I have to include any ADDITIONAL, important information/language in order to make the letter valid?

Thank you.

1 Answer


Answered on: 7/31/13, 10:29 am by Stephen Messutta

If you want an attorney involved, either you will need to send the notice to the attorney for review or let the attorney prepare the notice. You are asking for free legal advice.


Did you find this answer helpful?

0 Users found this answer helpful.

0 Attorneys agree with this answer.


Attorney address not available

Other answers from this attorney

Didn't find what you were looking for? Ask an Attorney!

Get answers from the top Attorneys
Ask Question

70 Answers given in the last few hours.

86611 Active attorneys ready to answer your question

Search Past Answers:
  Advanced Search