Legal Question in Construction Law in Florida

We are a subcontractor who has always received our deposit and progress draws from the owner even though there is a GC on the project. Now the contractor is not authorizing final pay. We did not file an N.T.O. (note: there is no notice of commencement) we completed the job 10 days ago today. We are past 45 days from start of project. Should we still fine an intent to lien to hopefully encourage owner of the country club to pay ? Would this be a breach of contract or could this be an equitable lien situation?


Asked on 3/22/11, 7:53 am

1 Answer from Attorneys

Alterraon Phillips APLaw, LLC

Since you are a subcontractor, I presume your contract is with the contractor and not with the owner (although they paid you directly). In this case you are correct in stating you have to issue the NTO within 45 days before or after starting the job for the lien to be valid. Then you have up to 90 days after the work is complete to file the lien. Does not mean you cannot file it but be prepared if it is contested, you may become liable for the other party's attorney fees.

In the case you reference your cause of action would be breach of contract against the contractor and third party beneficiary against owner. You just have to be sure and review your contract and understand what rights you have per the contract. If the contractor gets paid every 30 days and your contract says you get paid when the contractor does, you need to wait a little longer than 10 days. Every situation is different and I highly recommend you review the terms of your agreement. You also need to make sure they do not have a counter claim against you such as incomplete punchlist or work not in accordance with specifications.

Read more
Answered on 3/24/11, 8:29 pm


Related Questions & Answers

More Construction Law questions and answers in Florida