Legal Question in Construction Law in Pennsylvania

Signed contract for price, invoice different than contract

We signed a contract for a specific price for a heat pump/central air unit. The invoice came with an amount $800.00 more than the signed contract. Do we have to pay the additional amount? We did not receive any change order or anything stating why the difference in price.


Asked on 11/15/06, 4:40 pm

1 Answer from Attorneys

Charles A. Pascal, Jr. Law Office of Charles A. Pascal, Jr.

Re: Signed contract for price, invoice different than contract

Well, my first question would be, what are you not telling me? What's the additional $800 for?

If there was no unforeseen work, then no, you don't owe the $800. If there was, then more details are necessary.

Read more
Answered on 11/20/06, 2:06 pm