North Carolina  |  Construction Law

Legal Question

Asked on: 7/21/13, 8:23 am

I hired a contractor to finish my basement and the estimate to complete was 10 weeks. It's week 13 and the work is not complete. Is this considered a breach of contract?

Also, I was required to pay for labor in three separate payments at beginning, middle, and end. Two of the labor installments have been paid. The contractor asked me to pay a portion of the final payment up front in order to pay his subcontractors. Is this also considered a breach?

1 Answer


Answered on: 7/21/13, 9:58 am by John O'Neal

The contractor's failure to complete the work within the time specified in the contract very well could constitute a breach of contract. His requesting a portion of the final payment could be a breach but a true determination of your situation would require review of all written and signed documents by an experienced attorney. I would be hesitant to make any further payments especially if no payment is due at this time per your agreement---preferably written and signed by contractor----with the contractor.


Did you find this answer helpful?

0 Users found this answer helpful.

0 Attorneys agree with this answer.


O'Neal Law Office 7 Battleground Court, Suite 212 Greensboro, NC 27408

Other answers from this attorney

Didn't find what you were looking for? Ask an Attorney!

Get answers from the top Attorneys
Ask Question

70 Answers given in the last few hours.

86611 Active attorneys ready to answer your question

Search Past Answers:
  Advanced Search